You're currently browsing the Software Developers' Lounge section within the Software Development category of DaniWeb, a massive community of 402,036 software developers, web developers, Internet marketers, and tech gurus who are all enthusiastic about making contacts, networking, and learning from each other. In fact, there are 2,450 IT professionals currently interacting right now! Registration is free, only takes a minute and lets you enjoy all of the interactive features of the site.

payment structure for development project

Join Date: Dec 2005
Posts: 3,393
Reputation: Salem has much to be proud of Salem has much to be proud of Salem has much to be proud of Salem has much to be proud of Salem has much to be proud of Salem has much to be proud of Salem has much to be proud of Salem has much to be proud of Salem has much to be proud of 
Rep Power: 21
Solved Threads: 385
Colleague
Salem's Avatar
Salem Salem is offline Offline
void main'ers are DOOMed

Re: payment structure for development project

  #2  
Sep 13th, 2007
> 50% at the end of 2 weeks when database design and architecture is finalized
Unless the system is that simple, the design is never the final representation of the system. Sooner or later, some unanticipated snag (or gaping hole) will be found which upsets the whole program.
Yes, 50% for this is extreme IMO.

> 20% at the end of 22 weeks upon project completion.
I would expect 4 or 5 milestones in this, each of which would trigger a payment.

Split the pot 50:50
One pot is paid pro-rata on the basis of work being done. Each week you get a statement of activities and achievements, and you hand over a bit of money.
The other pot is split into say 5 equal parts, and each part is handed over at the successful completion of a milestone.

If they still want an advance, then I would bargain. Maybe even consider some Escrow arrangement if you feel the amount up front is too much. Make sure you have a good contract.
If you dance barefoot on the broken glass of undefined behaviour, you've got to expect the occasional cut.
Do not PM me for help; You'll be ignored, or told to learn to read.
Do not ask me if I'm muslim - I'm not. Nor do I care about yours or anyone else's mysticism. Religion is a matrix, take the RED PILL.
Reply With Quote  
All times are GMT -4. The time now is 10:57 pm.
Forum system based on vBulletin Copyright ©2000 - 2008, Jelsoft Enterprises Ltd.
©2003 - 2008 DaniWeb® LLC