hungry_for_info 0 Junior Poster in Training

Unbox of everything below
Rack (4) APC PDU’s, configure via serial cable (ip address / password) – (racking will consist of zip tieing them and having corporate colo connect them to the power bus)
Rack (4) cisco switches, paste in configuration via in console
Rack (2) Brocade Switches, provide me with teamveiwer access to configure them via console cable
Run (1) patch cable per apc to our first row cisco switch
Run (1) patch cable per cisco switch to our first row cisco switch
Run (2) patch cables per brocade back to our brocade switch in the first row
Install rails (66) servers
Rack (66) servers
Connect power cables for (66) server
Configure ipmi
Connect (3) cables per server to switches (nic 1 to brocade, nic 2 to cisco, ipmi to cisco)
Label servers, switches and pdus

Be a part of the DaniWeb community

We're a friendly, industry-focused community of developers, IT pros, digital marketers, and technology enthusiasts meeting, networking, learning, and sharing knowledge.